🇬🇪 20-Day Express Delivery|5-Ton HD European Single Girder Crane Successfully Installed in Georgia Automotive Plant

Project Completion: August 28, 2025 | Location: Tbilisi, Georgia
图片处理 14

 Antop 5T HD European single girder crane in operation at an automotive components factory in Georgia


Project Overview

Key Detail
Specification
Client Type
Local equipment supplier (procuring for end-user: automotive parts manufacturer)
Application
Material handling in welding & assembly workshop
Core Challenge
30-day delivery deadline for CE-compliant crane with dual-speed precision control
Antop Solution
Customized HD European single girder crane + Schneider electrical system + dual-mode wireless control

Technical Specifications                                                                             

Parameter
Specification
Model
HD European Single Girder Overhead Crane
Capacity
5 tons
Span
18 meters
Lifting Height
6 meters
Lifting Speed
0.8 / 5 m/min (dual-speed for precise positioning & efficient handling)
Trolley Travel Speed
2–20 m/min (VFD controlled)
Bridge Travel Speed
3–30 m/min (VFD controlled)
Duty Class
A5 (suitable for moderate-frequency operations)
Electrical System
Schneider contactors & circuit breakers (IEC 60204-1 compliant)
Hoist
Premium Chinese brand electric hoist (IP54 protection)
Control Method
Pendant push-button + 2.4GHz industrial wireless remote (30m range)
Power Supply
380V / 50Hz / 3PH

Core component: Schneider electrical system ensures stable operation in Georgia’s 40°C summer conditions


Project Timeline: From Inquiry to Delivery in Just 27 Days

▸ June 28, 2025|Urgent Inquiry Received
A Georgian equipment supplier contacted Antop via LinkedIn, urgently requesting quotations for 2 HD European single girder cranes for their end-client’s production line expansion. Their message emphasized: “Must arrive within 30 days—any delay will halt the entire production line launch.”
▸ June 30|Precision Quotation Delivered
Antop’s sales engineer provided a component-by-component quotation (12 items including main girder, end trucks, hoist, electrical cabinet) within 24 hours, featuring:
  • Dual-currency pricing (CNY/USD)
  • 5% early-bird discount for first-time buyers
  • 20-day express production schedule (vs. standard 35 days)图片处理 12
▸ July 5|Contract Signed
After comparing 3 Chinese suppliers, the client chose Antop for:
Transparent pricing with zero hidden costs
Guaranteed 20-day production cycle (competitors required 30+ days)
Schneider electrical original warranty certificate provided upfront
30% deposit paid same day; contract activated.
▸ July 6–25|Express Production Executed
  • Production team activated “green channel”: priority scheduling + weekend shifts
  • WhatsApp project group updated client every 48 hours with production videos (cutting → welding → painting → assembly → testing)
  • Day 18: Completed 72-hour load test (125% static load + 110% dynamic load cycling)
▸ August 28|Successful Delivery & Commissioning
Equipment shipped from Tianjin Port, arrived at Poti Port after 12 days. Client accepted on first inspection. Installation & commissioning completed in 2 days—production line launched on schedule.

▲ Left: Equipment arrival at Poti Port, Georgia | Right: Client engineer signing acceptance certificate


Client Testimonial

“We were skeptical whether any Chinese supplier could meet the 30-day deadline, but Antop not only delivered 10 days early—they provided fully transparent production videos throughout. The Schneider electrical system runs flawlessly in Georgia’s 40°C heat, and the wireless remote significantly improved operator safety. After 3 months of zero downtime on the first unit, we’ve already placed our second order.
— David T., Procurement Director | GeoMach Supply (Georgian Equipment Distributor)

Why Antop Delivers on Tight Deadlines

Challenge
Antop’s Solution
Short lead time
20-day express production lane (subject to schedule confirmation)
Strict electrical standards
Schneider/Siemens components standard; CE/ISO certificate package included
Time zone barriers
Dedicated WhatsApp project group with English/Russian/Chinese support
Acceptance risk
Free FAT (Factory Acceptance Test) video + third-party inspection report