🇬🇪 20-Day Express Delivery|5-Ton HD European Single Girder Crane Successfully Installed in Georgia Automotive Plant
Project Completion: August 28, 2025 | Location: Tbilisi, Georgia
Antop 5T HD European single girder crane in operation at an automotive components factory in Georgia
Project Overview
Technical Specifications
Core component: Schneider electrical system ensures stable operation in Georgia’s 40°C summer conditions
Project Timeline: From Inquiry to Delivery in Just 27 Days
▸ June 28, 2025|Urgent Inquiry Received
A Georgian equipment supplier contacted Antop via LinkedIn, urgently requesting quotations for 2 HD European single girder cranes for their end-client’s production line expansion. Their message emphasized: “Must arrive within 30 days—any delay will halt the entire production line launch.”
▸ June 30|Precision Quotation Delivered
Antop’s sales engineer provided a component-by-component quotation (12 items including main girder, end trucks, hoist, electrical cabinet) within 24 hours, featuring:
- Dual-currency pricing (CNY/USD)
- 5% early-bird discount for first-time buyers
- 20-day express production schedule (vs. standard 35 days)

▸ July 5|Contract Signed
After comparing 3 Chinese suppliers, the client chose Antop for:
Transparent pricing with zero hidden costs
Guaranteed 20-day production cycle (competitors required 30+ days)
Schneider electrical original warranty certificate provided upfront
30% deposit paid same day; contract activated.
▸ July 6–25|Express Production Executed
- Production team activated “green channel”: priority scheduling + weekend shifts
- WhatsApp project group updated client every 48 hours with production videos (cutting → welding → painting → assembly → testing)
- Day 18: Completed 72-hour load test (125% static load + 110% dynamic load cycling)
▸ August 28|Successful Delivery & Commissioning
Equipment shipped from Tianjin Port, arrived at Poti Port after 12 days. Client accepted on first inspection. Installation & commissioning completed in 2 days—production line launched on schedule.
▲ Left: Equipment arrival at Poti Port, Georgia | Right: Client engineer signing acceptance certificate
Client Testimonial
“We were skeptical whether any Chinese supplier could meet the 30-day deadline, but Antop not only delivered 10 days early—they provided fully transparent production videos throughout. The Schneider electrical system runs flawlessly in Georgia’s 40°C heat, and the wireless remote significantly improved operator safety. After 3 months of zero downtime on the first unit, we’ve already placed our second order.“
— David T., Procurement Director | GeoMach Supply (Georgian Equipment Distributor)
Why Antop Delivers on Tight Deadlines
Your Urgent Project—Delivered in 20 Days
Whether you need a single trial unit or bulk procurement, Antop delivers:
✓ European & Chinese design standards ✓ 1–500 ton full range ✓ 120+ countries served